2015 Crack & Joint Sealing Update
On Thursday, March 12 and Friday, March 13, 2015, contractor Circle C Paving will begin performing the annual crack and joint maintenance on the following streets for the City of Salina:
N. Kenwood Park Drive (Prescott Avenue to Oakdale Drive);
Oakdale Avenue (Oakdale Drive to Ash Street).
“Road Work Ahead” signs will be placed in advance of active work zones, and temporary single-lane closures are to be expected. Motorists are asked to proceed with caution when approaching work zones for the safety of the crews performing the work. Access to properties within work zones will be maintained at all times.