News Releases

7/17/2015 - 2015 Microsurfacing Road Work

Kent Johnson
Civil Engineer
785-309-5725
Kent.johnson@salina.org

 

2015 Microsurfacing Road Work

Beginning on Monday, July 20th, City contractors will begin applying microsurfacing on various streets within the city limits. The schedule for July 20 – July 24 is as follows:

Monday
July 20 Fourth Street (Crawford to Center)
Planet Avenue (Magnolia to Saturn)
Planet Avenue (300’ North of Belmont to Key)
Santa Fe Avenue (Republic to Crawford)

Tuesday
July 21 Oakdale (Oakdale Dr. to Ash)
N. Kenwood Park Drive (Prescott to Oakdale Dr.)
Fourth Street (Claflin to Beloit)

Wednesday
July 22 Faith Drive (Republic to McAdams)
Courtney Drive (Cul de Sac to Republic)
Republic Avenue (Osborne to Roach)
Cherokee Drive (Republic to Pueblo)

Thursday
July 23 Cloud Street (Westwood Drive to Broadway)
Cedar Ridge Drive (Marymount to Old Cloud Street)

Friday
July 24 Bret Avenue (115’ south of Post Oak to Colonial)
Bret Avenue (115’ south of Post Oak to Neal)
Republic Avenue (Ohio to Republic Cir)
Republic Circle

The work will include applying the asphalt surface treatment and placing temporary pavement markings.

The contractor will begin setting traffic control at 7 am. Temporary traffic control and flaggers will be present to direct vehicles through the work zones and maintain traffic flow; traffic will be reduced to single lanes in both directions during paving. Residences and businesses will be notified if access to driveways will be restricted while work is performed.

Microsurfacing is a method of pavement surface treatment which prolongs the serviceability of streets by creating a moisture-resistant barrier while increasing the rideability. This process has been successfully used in Salina for many years. Combined with joint and crack sealing, this surface treatment program extends the service life of pavement.

For additional questions, contact the Department of Public Works at 785-309-5725