9/18/2015 - 2015 Mill and Inlay Road Work Update

Kent Johnson
Civil Engineer
(785) 309-5725
kent.johnson@salina.org

2015 Mill and Inlay Road Work Update

The City’s annual Mill and Inlay work will continue on Monday September 21, 2015.

The schedule for September 21 – September 25, weather permitting, is as follows:

September 21 Page Avenue – Talley Drive to Roberts Avenue
  Willis Avenue – Page Avenue to Haskett Ave
  
September 22 Haskett Ave – Willis Avenue to Cloud Street
  Smith Ave – Haskett Avenue to Broadway Blvd

September 23 Faith Drive – Mcadams Road to 1100 feet north of Mcadams Road
  Fairdale Rd – Crawford Street to Village Lane
  Walnut Street –  RR Tracks to 9th Street

September 24 Fairdale Rd – Crawford St to 2200 feet south of Crawford Street
  Front Street – Crawford Street to Prescott Ave
    
September 25 Walnut Street –  RR Tracks to 9th Street
  Planet Avenue – Sullivan Avenue to 650 feet north of Sullivan Avenue
  Debold Avenue –  9th Street to Market Place

While the work is in progress, individual roads will be closed to through traffic. The contractor will begin setting traffic control at 7 am. Residences and businesses will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles or equipment left on the street on the day paving is scheduled, may be towed at the owners’ expense.

This project is a major component of the 2015 Street Maintenance Program. The project consists of milling the existing asphalt street surface 1.5” deep and then resurfacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after resurfacing is complete.

For additional questions, contact the Department of Public Works at 785-309-5725.