3/18/2016 - Mill and Inlay, March 21 – March 25

Bill Shelby
Public Works 
(785) 309-5725
bill.shelby@salina.org

Mill and Inlay, March 21 – March 25

The City contractors will continue the annual Asphalt Mill and Inlay project on various streets in the City of Salina.

The schedule for March 21 – March 25, weather permitting, is as follows:

Monday, March 21
Albert Avenue – Quincy Street to Roach Street
Belmont Boulevard – Roach Street to Ohio Street
Linda Lane – Arrowhead Lane to Neal Avenue
Oxford Drive – Belmont Boulevard to Ohio Street

Tuesday, March 22
Belmont Boulevard – Roach Street to Ohio Street
Cloud Street – Roach Street to Quincy Street
Oxford Drive – Belmont Boulevard to Ohio Street

Wednesday, March 23
Cloud Street – Roach Street to Quincy Street
5th Street – Republic Avenue to Prescott Avenue

Thursday, March 24
Cloud Street – Roach Street to Quincy Street
5th Street – Republic Avenue to Prescott Avenue

Friday, March 25
Cloud Street – Roach Street to Quincy Street
5th Street – Republic Avenue to Prescott Avenue

While the work is in progress, the individual roads will be closed to through traffic. The contractor will begin setting traffic control at 7 am. Residences and businesses will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles, or equipment, left on the street on the day paving is scheduled may be towed at the owners expense.

This project is a major component of the 2016 Street Maintenance Program. The project consists of milling the existing asphalt street surface 1.5” deep and then resurfacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after resurfacing is complete.

For additional questions, contact the Department of Public Works at 785-309-5725.