7/8/2016 - 2016 Chip Seal Road Work to Begin

Contact: Kent Johnson, Civil Engineer
(785) 309-5725
kent.johnson@salina.org

2016 Chip Seal Road Work to Begin

Beginning on Monday, July 11th, City contractors will begin chip sealing on various streets within the city limits. The schedule for July 11 – 15 is as follows:

Monday

July 11

Airport Road – inside Salina city limits

Bailey Court

Clay Ridge Court

Jumper Road

Kneubuhl Court

Rogers Court

Sutherland Court

Vortex Avenue

Wall Street

Tuesday

July 12

Arnold Court

Berschel Avenue

Hein Avenue

Scanlan Avenue – north of Tony’s Road

Wednesday

July 13

3rd Street – Pacific Avenue to Euclid Avenue

Diamond Drive – in front of Motel 6 and IHOP

Monarch Road

Thomas Park

Thursday

July 14

Old 40 Highway – inside Salina city limits

Old 40 Highway Court

Pacific Avenue – Kenny’s Autos to Ohio Street

Pacific Court

Friday

July 15

Bromac Avenue

Dewey Street – west of Bromac Avenue

Edison Place

Lakewood Park Drive and Parking Lots


The work will include applying the asphalt surface treatment and placing temporary pavement markings.

The contractor will begin setting traffic control at 7 am. Temporary traffic control and flaggers will be present to direct vehicles through the work zones and maintain traffic flow; traffic will be reduced to single lanes in both directions during paving. Residences and businesses will be notified if access to driveways will be restricted while work is performed. On-street parking in work zones will be prohibited. Any vehicles or equipment left on the street the day work is scheduled may be towed at the owners expense.

Chip Sealing is a method of pavement surface treatment which prolongs the serviceability of streets by sealing the surface. Combined with joint and crack sealing, this surface treatment program extends the service life of pavement.

For additional questions, contact the Department of Public Works at 785-309-5725.