7/13/2022 - Mill and Inlay Work Begins 7/13/2022

MILL AND INLAY WORK BEGINS

 

On Wednesday, July 13th, APAC Shears of Salina began working on the City of Salina’s annual asphalt mill and inlay project.  The schedule is as follows, weather permitting:

 

 

M

T

W

TH

F

11

12

13

14

15

Bishop, College to 9th

M

T

W

TH

F

13th, Pacific to Woodland

M

T

W

TH

F

Pacific, Santa Fe to Front

M

T

W

TH

F

 

The work consists of milling the existing asphalt street surface 1.5” and replacing it with new asphalt to rehabilitate and preserve the pavement section.  Permanent pavement markings will be placed shortly after the resurfacing.

 

The work on local streets will be completed with total closures, and residents will be given sufficient notice and accommodations.  The work on arterial streets will be completed with lane closures.  Motorists should expect modest delays and are encouraged to avoid the work zones altogether if possible.

 

The $916,000 project is a major component of the City of Salina's $4.7 million 2022 maintenance capital improvement program.