8/20/2014 - 2014 Asphalt Mill & Inlay Road Work Update

Kent Johnson, P.E.
Civil Engineer
(785) 309-5725
kent.johnson@salina.org


2014 Asphalt Mill & Inlay Road Work Update

Location and Proposed Schedule
Saturn Avenue: Hageman Avenue to Planet Avenue 8/20 - 8/21
Bailey Road: Centennial Road to Arnold Avenue 8/21 - 8/29
Arnold Avenue: Bailey Road to General Jim Road 8/21 - 8/29
General Jim Road: Arnold Avenue to Scanlan Avenue 8/21 - 8/29
Belmont Boulevard: Magnolia Road to Roach Street 8/27 - 8/29
Ohio Street: McAdams Road to Faith Avenue 8/29 - 9/3
Ohio Street: Iron Avenue to Elm Street 8/29 - 9-3

Duration of Work: 10 working days (Monday - Friday)

On Wednesday, August 19, APAC-Kansas Inc., Shears Division, will continue milling & inlaying the streets according to the schedule given above, weather permitting. 

Saturn Avenue, Bailey Road, Arnold Avenue and General Jim Road will be closed to through traffic; Belmont Boulevard and Ohio Street will be constructed allowing through traffic on alternating lanes.  Generally, the outside lanes are milled and resurfaced first with traffic on the inside lanes, thereafter traffic is switched to the outside lanes while the inside lanes are resurfaced.

This project is a major component of the 2014 Street Maintenance Program.  The project consists of approximately 6.0 miles of milling the existing asphalt street surface 1.5” deep, and then resurfacing it with new asphalt to rehabilitate and preserve the pavement section.  Permanent pavement markings will be placed shortly after resurfacing is complete.

As with any street project, there will be some inconvenience to the public.  Traffic flow within the work zone will be restricted during working hours, and detour signage and flaggers should be expected.  Access to local businesses and homes will be maintained.  However, motorists should be prepared for minor delays.  Residences and businesses will be notified if access to driveways will be restricted while work is performed.  On-street parking in work zones will be prohibited.  Any vehicles or equipment left on the street the day work is scheduled may be towed at the owners expense.

For additional questions, contact the Department of Public Works at 785-309-5725.

###